These are all the specific activities required to prepare the oil or gas-in and to bring the plant in operation: 

  • Put on pipe work and vessel on line (valves, PSV, locking devices…) 
  • Check that all valves subject to a ‘‘locked status’’ are in the locked open or locked closed position, in accordance with the Approved drawings and procedures; 
  • Check all isolations by spading and blinds are in accordance with the Approved drawings and procedures; 
  • Establish the list of available equipment; 
  • Prepare the ICSS inhibition sheets that list the inhibition that will be required for oil-in or gas-in; 
  • Perform the audits and technical reviews scheduled to be necessary for the issuance of
  • the ’’ready for oil/gas-in’’ certificate;
  • Check that all punch list items needed to be cleared before start-up; 
  • Complete first fills; 
  • Ensure safety equipments and critical utilities availability and reliability;
  • Carry out the final safety tests (ESD,F&G, deluge, …) ;
  • Obtain final clearance for oil/gas in;


At this stage the ‘’Ready for Function Test Certificate’’ shall be issued. It relates to the specific ‘’oil/gas-in’’ milestone to which may be associated a number of prerequisite. 
After issuance of the ‘’Ready for Function Test Certificate’’ are performed all the following activities required to start-up the plant with first introduction of the feedstock into the plant :

  • Bring the process in operation (Oil/gas-in, water injection…) 
  • Carry out outstanding Commissioning Operational test 
  • Carry out the Performance tests to prove the plant and equipment and design capacities products specifications, etc. 


Start-Up dossier 
All documentation pertaining to the Start-up activity is compiled in a specific Dossier. They contains all the information required to demonstrate that a system has reached the ready for hydrocarbon introduction status. 
Its content is the following: 

  • First Start-Up sequence and procedure with all notes taken during the start-up for further update of the procedure 
  • Marked-up P&IDs showing the status for blinds and spades at time of transfer to the OPERATOR. 
  • Ready for Start-up Certificate 
  • Updated Punch List 
  • Operational Test Procedure, reports, and Operational Test Certificate carried out during the start-up phase 
  • Routine Start-up procedures, Emergency and routine shutdown procedures.

Start-Up Engineering!


Start-up and performance test preparation 
It mainly includes the following activities, but not limited to : 

  • Clear identification, programming and planning of the activities with / without Hydrocarbon (Methanol, Diesel, …) 
  • Definition of ‘’ready for oil/gas-in’’ activities 
  • Pre-requirements to start-up a task 
  • Operational risk assessment and environmental assessment impact
  • Resource/training/knowledge definition and certification as needed.


Start-Up Documents 

These activities typically include, but not limited to: 

  • Gather VENDOR and PROCESS LICENSOR START-UP documentation. 
  • Prepare detailed start-up procedures
  • Prepare associated start-up check lists 
  • Define list and description of ‘’ready for oil/gas-in’’ activities (technical checks, safety audits, organizational audits, etc…) 
  • Prepare detailed Performance Test Procedures. 
  • Prepare planning, resource mobilization plan, etc… 
  • List documents to be included in the ‘’Ready For Operation’’ dossier. 


Start-Up performance 
The team in charge of start-up shall conduct the ‘’ready for oil/gas-in’’ activities. 